PROCUREMENT OF MANAGED SERVICES FOR PRIMARY AND SECONDARY ISP CONNECTIVITY FOR AIRPORT OPERATIONS
USER ACCEPTANCE TEST (UAT) FORM
Ninoy Aquino International Airport (NAIA)
Site/Facility: Coordinates:
Terminal Zone: Date of Acceptance:
Address:
1. EQUIPMENT
Equipment Brand/ Model Serial Number MAC Address Status
Access Point 1
Modem
2. BANDWIDTH TESTING
ACCESS POINT ZONE/LOCATION Download (Mbps) Upload (Mbps) Latency (ms) Status
ACCESS POINT 1
3. OTHER REQUIREMENTS REMARKS
1. Signage provided, properly installed and met the required minimum size.
A4: per Information Desk (Arrival and Departure)
2. Signage provided, properly installed and met the required minimum size.
Banner Tarpaulin: per Lounge
3. ISP 1: 10 Gbps
4. ISP 2: 10 Gbps
Overall Result: Remarks:
Inspected by:


Engineer III, DICT-IMB-DRRMD

Information Systems Analyst II, DICT-IMB-CIIMD

Computer Programmer II, DICT-IMB-DRRMD
Accepted By:


DICT End User Position
SITE PHOTOS - MAIN EQUIPMENT & ACCESS POINTS
πŸ“· Click to upload FaΓ§ade
FAÇADE
πŸ“· Click to upload Modem
MODEM
πŸ“· Upload AP 1
SPEED TEST PHOTOS
πŸ“· Upload Speedtest Primary ISP
πŸ“· Upload Speedtest Secondary ISP
πŸ“· Upload Speedtest AP 1
CONFIGURATION AND INFORMATION SCREENSHOTS
πŸ“· Upload SSID Screenshot
πŸ“· Upload Captive Portal Screenshot
ADDITIONAL VALIDATION SCREENSHOTS (1/3)
πŸ“· Upload Failover Simulation Logs
AUTOMATIC FAILOVER SIMULATION LOGS
πŸ“· Upload Historical Alarms
EXTRACTION OF HISTORICAL ALARMS
ADDITIONAL VALIDATION SCREENSHOTS (2/3)
πŸ“· Upload Connected Users' MAC Address
EXTRACTION OF CONNECTED USERS' MAC ADDRESS
πŸ“· Upload Data Usage Extraction
EXTRACTION OF DATA USAGE
ADDITIONAL VALIDATION SCREENSHOTS (3/3)
πŸ“· Upload Packet Loss Test Screenshot
PACKET LOSS
SIGNAGES
πŸ“· Upload Signage 1
SIGNAGE 1